Project Duration
Stipulated Date of Commencement
June 15 2018
Stipulated Date of Completion /
Likely Date of Completion June 30 2018
Likely Date of Completion June 30 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,204.00
Awarded for
₹ 45,312.00
Project highlights
The scope of work invloves installation of decorative street light poles along with the cabling work and providing foundations for street lights.