Project Duration
Stipulated Date of Commencement November 25 2010
Actual Date of Completion March 11 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,07,10,082.00
Awarded for ₹ 6,22,69,573.00
Final Cost of Project ₹ 86,264,969.00
 
Contractors
M/s. Shilpi Constructions
Consultants
M/s. Rahul Deshpande & Associates
 