Project Duration
Stipulated Date of Commencement
February 27 2014
Actual Date of Completion
July 15 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,232,612.00
Awarded for
₹ 9,932,510.00
Project highlights
The scope of work involves supply and installation of decorative street light poles on the Service road.
Contractors
M/s. Goa Friends Engineering and Electricals Pvt. Ltd
Consultants
M/s. Nitin Arolkar
See Similar Projects
Interior & furniture works.
View ProjectSupply,Installation,Testing and Commissioning of streetlight poles and fixtures along with allied electrical works for the stretch from NIO Circle to Miramar circle, NIO circle to Rajbhavan, NIO circle to Dona Paula Jetty & NIO circle to Odxel Junction
View ProjectDismantling of HT overhead lines and supplying & laying of HT Underground cables at Porvorim