Project Duration
Stipulated Date of Commencement February 27 2014
Actual Date of Completion July 15 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,232,612.00
Awarded for ₹ 9,932,510.00

Project highlights

The scope of work involves supply and installation of decorative street light poles on the Service road.

 
Contractors
M/s. Goa Friends Engineering and Electricals Pvt. Ltd
Consultants
M/s. Nitin Arolkar
 