प्रकल्पाची कालावधी
सुरवात जावपाची थारायल्ली तारीख December 19 2014
पुराय जावपाची प्रत्यक्ष तारीख December 19 2018
स्थिती
100%
पुराय जाल्ले
खर्च (₹)
अदमास खर्च ₹ 326,394,633.00
दिले ₹ 383,810,938.44

प्रकल्प हायलायट्स

The scope of construction, completion & maintenance during the defect liability period of “UPGRADATION & BEAUTIFICATION OF ROAD NETWORK FROM SERAULIM TO COLVA BEACH – PHASE I comprises of :
Construction of Culverts in the following stretches
Two Box culverts in the stretches between Seraulim Junction to Colva Junction
One Box Culvert between Colva Junction & Sernabatim
Construction of two Box Culverts between Khareband Bridge to Ville Karle
Construction of RCC Retaining walls with Service ducts in the following stretches:
Both side in the stretches between Seraulim Junction to Colva Junction
One side between Colva Junction & Sernabatim
Construction of service ducts in the land portion in the specific area
Both side in the stretches between Seraulim Junction to Colva Junction
One side between Colva Junction & Sernabatim
Cross drainage works (RCC works)

 
Gallery Image
कंत्राटदार
M/s. H. S. Mehta
Gallery Image
सल्लागार
M/s. Construma Consultancy Pvt. Ltd.
 
Similar Projects

अशेच तरेचे प्रकल्प पळोवचे

Similar Project

Construction of Bus Stand at Shiroda – Phase II : Civil works, internal electrification and road

तपशील पळोवचे
Similar Project

Construction of Training Wall & upgradation of fishing jetty at Cutbona (South Goa). (Revised Scope of work) Construction of fishing jetty at Cutbona (South Goa).

तपशील पळोवचे
Similar Project

Development of infrastructure for Panaji Minor Port : Construction of Jetty at Brittona.

तपशील पळोवचे
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
अस्विकरण: राजभाशा संचालनालय, गोंय सरकारा वरवीं अणकारीत. टीप: खंयचेय स्थितींत कायदेशीर अर्थावणी खातीर इंग्लीश आवृत्तीक प्राधान्य दितले.