Project Duration
Start Date
26/4/2007
End Date
8/10/2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,644,386.00
Awarded for
₹ 34,552,373.00
Final Cost of Project
₹ 34,061,000.00

Contractors
M/s. Kirloskar Constructions & Engineers Limited, M/s. Kirloskar Constructions & Engineers Limited

Consultants
M/s. Construma Consultancy Pvt. Ltd.
Additional Work
This project involved 2 additional tasks. The details of the same available below
Status | Progress | Project Duration Start Date / End Date |
Cost (Rs.) Estimated / Awarded |
Consultants & Contractors | ||
---|---|---|---|---|---|---|
|
||||||
100% completed
|
16/7/2010 - 10/1/2011 |
₹ 1,985,905.00 / ₹ 2,183,970.00 |
M/s. Vijaykumar Sawant Associates
- M/s. Deshpande Constructions |
|||
|
||||||
100% completed
|
6/4/2010 - 21/9/2010 |
₹ 609,064.00 / ₹ 651,172.00 |
Inhouse
- M/s. Oman Enterprises |
|||

See Similar Projects

Upgradation & beautification of road network from Seraulim to Colva beach – Phase I.
View Project
Landscaping work.
View Project
Widening of roads and relocation of structures in Fatorda Constituency- Phase I
View Project