Project Duration
Stipulated Date of Commencement
February 07 2019
Stipulated Date of Completion /
Likely Date of Completion May 06 2019
Likely Date of Completion May 06 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,935,265.00
Awarded for
₹ 5,028,800.00
Project highlights
the project involved providing stainless steel 2 seaters at various location of GMC.
Contractors
M/s. B.S. Metal Fabrication
Consultants
In-house (GSIDC)
See Similar Projects
Maintenance/Renovation works of Community Health Centre at Valpoi . Maintenance Contract for 2 Nos lift of make M/s. Thyssenkrupp Elevators India for a period of three years.
View Project
Supply, installation, testing and commissioning of 13 Passenger with Stretcher Lifts at TB and Chest Disease Hospital, St.Inez – Goa
View Project
Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Passenger Elevator and Dumb waiter installed in the Library Block at Goa Medical College and Hospital, Bambolim for three years.
View Project