Project Duration
Stipulated Date of Commencement
July 05 2018
Stipulated Date of Completion /
Likely Date of Completion July 04 2021
Likely Date of Completion July 04 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 287,000.00
Awarded for
₹ 287,000.00
Project highlights
Maintenance of UPS system at GMC
Contractors
M/s. Vertiv Energy Pvt. Ltd.,
Consultants
In-house (GSIDC)
See Similar Projects
Supply, Installation, Testing and Commissioning of Cautery Machine
View Project
Supply, Installation, Testing and Commissioning of Cardiac Monitors, ECG machine, Defribrillators, etc.
View Project
Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Heart Lung Machine