Project Duration
Stipulated Date of Commencement
July 23 2006
Stipulated Date of Completion /
Likely Date of Completion October 22 2006
Likely Date of Completion October 22 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,144,443.00
Awarded for
₹ 1,210,535.00
Contractors
M/s. Chowgule Industries (I) Ltd.
Consultants
M/s. Madhav Kamat & Associates