Project Duration
Stipulated Date of Commencement
January 01 2021
Stipulated Date of Completion /
Likely Date of Completion March 31 2021
Likely Date of Completion March 31 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,082,830.00
Awarded for
₹ 1,309,825.00
Project highlights
Sewage treatment plant
Contractors
M/s. Samco Water Technologies
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College. S.H.: Supply, Installation, Testing & Commissioning of Tower air conditioning units for the Reading room in the Library at Goa Medical College.
View Project
Upgradation of Primary Health Centre at Shiroda, Goa – Operation Theatre Works.
View Project
Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa – Civil and plumbing works.
View Project