Project Duration
Stipulated Date of Commencement
May 26 2013
Stipulated Date of Completion /
Likely Date of Completion November 25 2013
Likely Date of Completion November 25 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,50,771.00
Awarded for
₹ 23,88,737.00
Contractors
M/s. Mohan Electricals
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD