Project Duration
Stipulated Date of Commencement
February 19 2010
Stipulated Date of Completion /
Likely Date of Completion July 18 2010
Likely Date of Completion July 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,076,253.00
Awarded for
₹ 13,168,155.00
Contractors
M/s. Imperial Engineering Company
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Fire fighting, fire alarm and PA System works
View Project
Medical gas and Vacuum System work
View Project
Electrical work.
View Project





