Project Duration
Stipulated Date of Commencement April 02 2011
Stipulated Date of Completion /
Likely Date of Completion
August 01 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 33,86,391.00
Awarded for ₹ 35,09,999.00
 