Project Duration
Stipulated Date of Commencement
April 02 2011
Stipulated Date of Completion /
Likely Date of Completion August 01 2011
Likely Date of Completion August 01 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 33,86,391.00
Awarded for
₹ 35,09,999.00
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
Datta Kare Associates