Project Duration
Stipulated Date of Commencement
March 24 2012
Stipulated Date of Completion /
Likely Date of Completion April 22 2012
Likely Date of Completion April 22 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,69,922.00
Awarded for
₹ 5,084,300.00
Project highlights
Loose Furnitures
Contractors
M/s. Concept Creators
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
False ceiling work.
View Project
Examination Hall cum Auditorium at Goa Medical College & Hospital
View Project
Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for 4 nos. of Emerson make 30 KVA UPS systems installed for Modular OTs 1-4 at Goa Medical College and Hospital, Bambolim for a period of three years.
View Project