Project Duration
Stipulated Date of Commencement
December 19 2009
Stipulated Date of Completion /
Likely Date of Completion August 18 2010
Likely Date of Completion August 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 37,738,817.00
Awarded for
₹ 37,340,650.00
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Construction of Lecture Hall at Goa Medical College & Hospital at Bambolim, Goa – Civil, Plumbing, Electrical, Lift, Fire Fighting & HVAC works.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa S.H.: Maintenance Contract for the UPS systems installed at Upgraded Cottage Hospital, Chicalim for a period of three years (2019-2022)
View Project
Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Surgical Instruments
View Project