Project Duration
Stipulated Date of Commencement
January 20 2011
Stipulated Date of Completion /
Likely Date of Completion May 14 2011
Likely Date of Completion May 14 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,22,007.00
Awarded for
₹ 38,60,325.00
Contractors
M/s. Hi-Tech Engineering Works
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.