Project Duration
Stipulated Date of Commencement
August 02 2011
Stipulated Date of Completion /
Likely Date of Completion July 11 2011
Likely Date of Completion July 11 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,158,024.00
Awarded for
₹ 6,849,926.00
Contractors
M/s. Vighneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
See Similar Projects
Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for Dubas make online UPS Systems and Servo Stabilizers installed in GMC Hospital Complex Bambolim forsix months.
View Project
Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim –Goa -SH-Supply, Installation, Testing and Commissioning of Central Nursing Station monitor and Multichannel monitors (5 channels with IBP Monitoring)
View Project
Construction of IInd Phase of Goa Dental College and Hospital at Bambolim, Goa – Furniture, Interior & Miscellaneous Works.
View Project