Project Duration
Stipulated Date of Commencement January 17 2014
Stipulated Date of Completion /
Likely Date of Completion
March 17 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,800,000.00
Awarded for ₹ 5,201,200.00
 
Gallery Image
Contractors
M/S. WIPRO GE HEALTHCARE PVT. LTD
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of soak pits.

View Project
Similar Project

Non Comprehensive Maintenance contract along with Manpower 24 x 7 for operating Medical Gas Distribution System for Oxygen, N2O, Air and Vacuum (Exclusive of oxygen manifold and Nitrous oxide Manifold) for GMC Bambolim Hospital and Medical block for a period of 3 years

View Project
Similar Project

Operation and maintenance of centralized air conditioning plant of Goa Medical College & Hospital – Replacement of AHUs.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.