Project Duration
Stipulated Date of Commencement June 16 2012
Actual Date of Completion September 13 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 16,183,092.00
Awarded for ₹ 14,742,636.40
Final Cost of Project ₹ 13,455,330.00

Project highlights

Furniture work

 
Contractors
M/s. Floor-Space
Consultants
Datta Kare Associates
 