Project Duration
Stipulated Date of Commencement November 08 2013
Actual Date of Completion November 15 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 485,329.00
Awarded for ₹ 527,295.00
Final Cost of Project ₹ 653,761.00

Project highlights

Refurbishment work of Kala Academy complex prior to IFFI 2013.

 
Contractors
M/s. Aditya P. Kamat Tarcar, M/s. Aditya P. Kamat Tarcar
Consultants
M/s. UCJ Architecture & Environment
 

See Similar Projects

Dismantling of HT overhead lines, supplying & laying of HT underground cables at Panaji – Cable work from EDC substation to Chimbel junction.

View Project

Upgradation of RMU

View Project

Supply, Installation, Testing & Commissioning of Bio Digester Plant

View Project
x