Project Duration
Stipulated Date of Commencement November 21 2014
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 49,325,978.00
Awarded for ₹ 54,600,581.10
Final Cost of Project ₹ 48,449,803.00

Project highlights

Conversion of electrical overhead lines to underground cables.

 
Contractors
M/s. Goa Friend’s Engineering & Electricals Pvt. Ltd
Consultants
M/s. Nitin Arolkar
 