Project Duration
Stipulated Date of Commencement
April 15 2013
Stipulated Date of Completion /
Likely Date of Completion February 14 2014
Likely Date of Completion February 14 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 73,147,104.47
Awarded for
₹ 76,784,870.55
Project highlights
Construction of approaches to Cumbarjua bridge including road link upto Khandola college
Contractors
M/s. Expanse India, M/s. Expanse India
Consultants
M/s. Vijaykumar Sawant Associates