Project Duration
Stipulated Date of Commencement August 14 2020
Stipulated Date of Completion /
Likely Date of Completion
November 13 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,452,762.00
Awarded for ₹ 2,214,000.00

Project highlights

work consists of installation of 33kV SF6 gas insulated RMU

 
Gallery Image
Contractors
M/s. Pristine Engineering Services
Gallery Image
Consultants
M/s. KICON Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of High Court Complex at Penha de Franca, Porvorim.Civil, Plumbing, Electrical, HVAC, Lift and Firefighting works

View Project
Similar Project

Facilitation Services, Installation, Testing & Commissioning of Theatre equipments.

View Project
Similar Project

Construction of houses for Tariwada landslide victims at Headland Sada, Vasco.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.