Project Duration
Stipulated Date of Commencement August 14 2020
Actual Date of Completion April 10 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,452,762.00
Awarded for ₹ 2,214,000.00
Final Cost of Project ₹ 2,612,520.00

Project highlights

work consists of installation of 33kV SF6 gas insulated RMU

 
Contractors
M/s. Pristine Engineering Services
Consultants
M/s. KICON Ltd.
 