Project Duration
Stipulated Date of Commencement
August 14 2020
Stipulated Date of Completion /
Likely Date of Completion November 13 2020
Likely Date of Completion November 13 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,452,762.00
Awarded for
₹ 2,214,000.00
Project highlights
work consists of installation of 33kV SF6 gas insulated RMU
Contractors
M/s. Pristine Engineering Services
Consultants
M/s. KICON Ltd.