Project Duration
Stipulated Date of Commencement March 06 2019
Stipulated Date of Completion /
Likely Date of Completion
June 05 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 15,230,447.71
Awarded for ₹ 17,882,969.02

Project highlights

Reconstrction of Panchayat Building.

 
Gallery Image
Contractors
M/s. Shivam Infratech
Gallery Image
Consultants
M/s. Datta Kare Associate
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Reconstruction Of Panchayat Building Of Village Panchayat Parra, Bardez, Goa – Interior Work – Balance Work “

100% completed
 
Project Duration
Stipulated Date of Commencement November 14 2021
Stipulated Date of Completion /
Likely Date of Completion
January 13 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,061,602.01
Awarded for ₹ 1,156,969.00

Project highlights

Interior work for Panchayat building

 
Contractors
Contractors
M/S. Creation Interior Contractors
Consultants
Consultants
M/s. Datta Kare Associate
Similar Projects

See Similar Projects

Similar Project

Supply, erection and commissioning of Diesel Generator Sets

View Project
Similar Project

Beautification of lake at Curtorim (Ralloitollem).

View Project
Similar Project

Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Pernem Taluka : Village Panchayat Complex, Mandrem

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.