Project Duration
Stipulated Date of Commencement
March 06 2019
Stipulated Date of Completion /
Likely Date of Completion June 05 2020
Likely Date of Completion June 05 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,230,447.71
Awarded for
₹ 17,882,969.02
Project highlights
Reconstrction of Panchayat Building.
Contractors
M/s. Shivam Infratech
Consultants
M/s. Datta Kare Associate
Sub Works
This project involved 1 sub works. The details of the same available below
1
Reconstruction Of Panchayat Building Of Village Panchayat Parra, Bardez, Goa – Interior Work – Balance Work “
100% completed
Project Duration
Stipulated Date of Commencement
November 14 2021
Stipulated Date of Completion /
Likely Date of Completion January 13 2022
Likely Date of Completion January 13 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,061,602.01
Awarded for
₹ 1,156,969.00
Project highlights
Interior work for Panchayat building
Contractors
M/S. Creation Interior Contractors
Consultants
M/s. Datta Kare Associate
See Similar Projects
Beautification and landscaping of Municipal Garden near Military Engineering Service at Panaji (Rose Garden)
View Project
Construction of Market Complex, Panchayat Office, Community Hall, Gymnasium, Village Library, Anganwadi and Fish Market at Assonora, Bardez, Goa – Phase I
View Project
Demolition and reconstruction of Market Complex at Bhoma Adcolna Panchayat Banastarim Goa -Civil, Plumbing, Electrical, HVAC, Lifts and Fire Fighting works
View Project





