Project Duration
Stipulated Date of Commencement
March 06 2019
Stipulated Date of Completion /
Likely Date of Completion June 05 2020
Likely Date of Completion June 05 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,230,447.71
Awarded for
₹ 17,882,969.02
Project highlights
Reconstrction of Panchayat Building.
Contractors
M/s. Shivam Infratech
Consultants
M/s. Datta Kare Associate
Sub Works
This project involved 1 sub works. The details of the same available below
1
Reconstruction Of Panchayat Building Of Village Panchayat Parra, Bardez, Goa – Interior Work – Balance Work “
100% completed
Project Duration
Stipulated Date of Commencement
November 14 2021
Stipulated Date of Completion /
Likely Date of Completion January 13 2022
Likely Date of Completion January 13 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,061,602.01
Awarded for
₹ 1,156,969.00
Project highlights
Interior work for Panchayat building
Contractors
M/S. Creation Interior Contractors
Consultants
M/s. Datta Kare Associate