Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion September 07 2020
Likely Date of Completion September 07 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 127,712,059.00
Awarded for
₹ 138,447,777.00
Project highlights
The projects includes demolition and reconstrcution of market complex at Bhoma , Adcolna . The proposed building has a total of 60 shops, separate spaces for the vegetable vendors and fish and meat vendors. A community hall of a total capacity 450 people.
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. Shiva Consultancy Services Pvt. Ltd.