Project Duration
Stipulated Date of Commencement
May 02 2015
Stipulated Date of Completion /
Likely Date of Completion June 01 2015
Likely Date of Completion June 01 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,325,881.00
Awarded for
₹ 1,127,228.50
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Effective Architectural Services