Project Duration
Stipulated Date of Commencement
October 05 2007
Actual Date of Completion
October 23 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 37,518,970.00
Awarded for
₹ 44,608,744.20
Final Cost of Project
₹ 40,435,886.00
Contractors
M/s. M. M. Naik & Co., M/s. M. M. Naik & Co.
Consultants
M/s. Vijaykumar Sawant Associates
See Similar Projects
Construction of Library Building at Margao.
View ProjectAdditional furniture items.
View ProjectDigital Multifunctional Copiers
View Project