Project Duration
Stipulated Date of Commencement August 19 2014
Actual Date of Completion August 18 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ Rate contract Rs. 3,00,00,000.00
Awarded for ₹ Rate contract Rs. 3,00,00,000.00
Final Cost of Project ₹ 9,761,065.44

Project highlights

Refurbishment of ornamental poles

 
Contractors
M/s. Goa Friend’s Engineering & Electricals Pvt. Ltd.
Consultants
In house
 

See Similar Projects

Supply, Installation, Testing and Commissioning of APFC panel and UPS Works

View Project

Construction of two number of sheds for treatment of dry waste within the Corporation of the City of Panaji (CCP) jurisdiction.

View Project

Establishing Infrastructure for the Organic Waste Management Facility at Patto, Panaji – Balance works

View Project