Project Duration
Stipulated Date of Commencement
October 29 2021
Stipulated Date of Completion /
Likely Date of Completion May 31 2024
Likely Date of Completion May 31 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 24,015,019.00
Awarded for
₹ 26,643,291.78
Project highlights
1. Built-up area:810 sqm.
2. Ground Floor – 5 Shops, Health Centre, Library, Gym House with Changing Rooms, Bank, Panchayat Administration Office & Cabins, Conference Room and Toilets.
Contractors
M/s. Shri Hari Krishna Construction
Consultants
M/s. Nilesh Salkar Associates