Project Duration
Stipulated Date of Commencement August 20 2010
Actual Date of Completion August 14 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 30,789,278.00
Awarded for ₹ 32,313,347.00
Final Cost of Project ₹ 24,162,291.00

Project highlights

Beautification work by providing pavers for footpaths and hotmixing of certain internal roads in Sanguem town

 
Contractors
M/s Shilpi Constructions
Consultants
in- House
 