Project Duration
Stipulated Date of Commencement
April 23 2010
Stipulated Date of Completion /
Likely Date of Completion June 20 2010
Likely Date of Completion June 20 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,900,530.00
Awarded for
₹ 1,988,414.00
Contractors
M/s. Kamaxi Constructions
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.