Project Duration
Stipulated Date of Commencement
December 11 2014
Actual Date of Completion
August 31 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,055,616.00
Awarded for
₹ 55,882,025.78
Final Cost of Project
₹ 33,324,440.00
Project highlights
Development of service road and site development at Mont Boa Vista which includes surface excavation ,laying of 40mm thick BM,25mm thick Asphalt Concrete , Providing and laying of BMC ,laterite masonary etc.
Contractors
M/s Jagdish Pai
Consultants
M/s Manguesh Prabhugaonkar