Project Duration
Stipulated Date of Commencement
December 29 2016
Actual Date of Completion
October 30 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,627,249.00
Awarded for
₹ 8,005,852.89
Final Cost of Project
₹ 14,000,000.00
Project highlights
Beautification with soft and hard landscaping work
Contractors
M/s. Gurudatt Gardeners & Developers
Consultants
M/s. Nitin Arolkar