Project Duration
Stipulated Date of Commencement
January 11 2020
Stipulated Date of Completion /
Likely Date of Completion April 10 2021
Likely Date of Completion April 10 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,972,727.66
Awarded for
₹ 22,700,250.00
Project highlights
Consists of a) Ground Floor having Panchayat office with Library, Post office, Electricity office, Gymnasium, cabins for Sarpanch, Secretary/ Talathi, Meeting room, Store room, Shops, Record room, Pantry & toilets.
b) First Floor having Community Hall having seating capacity of 350 persons with Stage and independent green rooms, Toilet Block and Ancillary room. The roof is covered with double skin galvalume roofing

Contractors
M/s. Shivam Infratech

Consultants
M/s Datta Kare Associates