Project Duration
Stipulated Date of Commencement January 11 2020
Stipulated Date of Completion /
Likely Date of Completion
April 10 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 19,972,727.66
Awarded for ₹ 22,700,250.00

Project highlights

Consists of a) Ground Floor having Panchayat office with Library, Post office, Electricity office, Gymnasium, cabins for Sarpanch, Secretary/ Talathi, Meeting room, Store room, Shops, Record room, Pantry & toilets.
b) First Floor having Community Hall having seating capacity of 350 persons with Stage and independent green rooms, Toilet Block and Ancillary room. The roof is covered with double skin galvalume roofing

 
Gallery Image
Contractors
M/s. Shivam Infratech
Gallery Image
Consultants
M/s Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Fire Fighting, Fire Alarm and PA System.

View Project
Similar Project

Electrical work.

View Project
Similar Project

Air conditioning

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.