Project Duration
Stipulated Date of Commencement
February 13 2009
Stipulated Date of Completion /
Likely Date of Completion February 22 2009
Likely Date of Completion February 22 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 310,500.00
Awarded for
₹ 277,500.00
Contractors
M/s. Infinity Modules Ltd.
Consultants
M/s. Architecture Autonomous / M/s. Mahimtura Consultants Pvt. Ltd.