Project Duration
Stipulated Date of Commencement
December 31 2016
Actual Date of Completion
December 15 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,347,081.22
Awarded for
₹ 15,293,867.65
Final Cost of Project
₹ 16,845,242.34
Project highlights
The project consists of Construction of the proposed building in a plot of Area 35375.00 SQ.M. located at Panchawadi, Village in Ponda Taluka situated in North Goa District. Work includes construction of building consisting of 6 nos. Shops on Ground floor, Panchayat office on first floor and Community Hall of 300 persons seating Capacity on Second floor. It’s a G+2 building.
Contractors
M/s Trupti Construction
Consultants
M/s creative Abode
Sub Works
This project involved 1 sub works. The details of the same available below
1
Upgradation of Infrastructure in Rural Areas Under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme 2013 -Construction of Panchayat Ghar V.P. Panchawadi- Loose Furniture works”
100% completed
Project Duration
Stipulated Date of Commencement
September 17 2019
Stipulated Date of Completion /
Likely Date of Completion October 15 2019
Likely Date of Completion October 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 784,900.00
Awarded for
₹ 610,000.00
Final Cost of Project
₹ 719,800.00
Project highlights
Furniture Work
Contractors
M/s. Trident Enterprises
Consultants
M/s. Creative Abode