Project Duration
Stipulated Date of Commencement June 29 2007
Actual Date of Completion June 30 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,659,145.00
Awarded for ₹ 24,825,361.12
Final Cost of Project ₹ 29,634,858.00

Project highlights

The total built-up area is 1,507.49 sq. m. The ground floor of the market houses stalls of fish and vegetable vendors. Also, there is provision for a bank with toilet, post office, electricity office, health centre with toilet, shops, etc.
The first floor consisst of Panchayat office with cabins for the Sarpanch, Secretary, conference hall and gymnasium. The second floor consists of a multipurpose hall with stage, green rooms and toilets.

 
Contractors
M/s. M. B. Kinlekar
Consultants
M/s. Datta Kare Associates
 