Project Duration
Stipulated Date of Commencement
December 11 2014
Stipulated Date of Completion /
Likely Date of Completion February 10 2015
Likely Date of Completion February 10 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,582,490.00
Awarded for
₹ 4,199,999.00
Project highlights
Additional AC works required for completion of project
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Package II (VP Siridao, VP Goa Velha, VP Curca).
View Project
Construction of Panchayat Complex at Chicalim
View Project
Providing and Maintaining Event Management facilities for Exposition 2014 at Old Goa
View Project