Project Duration
Stipulated Date of Commencement March 18 2019
Stipulated Date of Completion /
Likely Date of Completion
January 15 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 19,396,779.97
Awarded for ₹ 19,994,471.03

Project highlights

The details of project are as follows:
• Name of the Client : Directorate of Panchayat.
• Executing Agency : GSIDC
• Name of the Consultant : M/s. Bhaskar Wagle
• Total plot area : 5100.00 Sq.M.
• Total Built-Up area : 781.66 Sq. M.
• The estimated cost of the work : Rs.1,93,96,779.97.
Design Concept
• The building is a Ground plus 2 RCC structure.
• The building shall include 6 Shops on ground floor, cabin for Sarpanch, Secretary, Talathi, meeting room, Panchayat office, Library on first floor and Multipurpose hall on second floor.
• The building shall have adequate parking facilities for four and two wheelers.
• A barrier free environment has been provided through an access ramp at the ground level and an elevator for upper levels.

 
Gallery Image
Contractors
M/s. Mahabaleshwar M. Naik & Co.
Gallery Image
Consultants
M/s. Bhaskar Wagle & Associates
 
Similar Projects

See Similar Projects

Similar Project

Additional civil work.

View Project
Similar Project

Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Panchayat Ghar For Village Panchayat Sarzora – Salcete

View Project
Similar Project

Stage lighting

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.