Project Duration
Stipulated Date of Commencement
November 10 2011
Actual Date of Completion
April 05 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,549,401.00
Awarded for
₹ 1,625,878.00
Final Cost of Project
₹ 1,504,488.00
Project highlights
Medical Gas & Other Connected works for OTs.
Contractors
M/s. Medical Systems (I) Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
– Office furniture and miscellaneous works.
View ProjectSupply, installation, testing & commissioning of portable OT light.
View ProjectSupply Installation Testing & Commissioning of water Heater & Purifier
View Project