Project Duration
Stipulated Date of Commencement November 10 2011
Actual Date of Completion April 05 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,549,401.00
Awarded for ₹ 1,625,878.00
Final Cost of Project ₹ 1,504,488.00

Project highlights

Medical Gas & Other Connected works for OTs.

 
Contractors
M/s. Medical Systems (I) Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 