Project Duration
Stipulated Date of Commencement
December 17 2008
Actual Date of Completion
January 31 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 263,660.00
Awarded for
₹ 392,000.00
Contractors
M/s. Oman Electricals
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.