Project Duration
Stipulated Date of Commencement
November 06 2008
Actual Date of Completion
October 20 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 24,932,899.00
Awarded for
₹ 19,636,164.00
Contractors
M/s. Imperial Engineering Company
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.