Project Duration
Stipulated Date of Commencement
February 07 2019
Stipulated Date of Completion /
Likely Date of Completion June 06 2019
Likely Date of Completion June 06 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,568,649.00
Awarded for
₹ 6,686,897.40
Project highlights
Office furniture and miscellaneous works.
Contractors
M/s. Virender Kumar & Co.,
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.