Project Duration
Stipulated Date of Commencement
August 31 2013
Stipulated Date of Completion /
Likely Date of Completion October 30 2013
Likely Date of Completion October 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,707,183.00
Awarded for
₹ 1,770,500.00
Contractors
M/s. Mediconz International
Consultants
In-house (GSIDC)