Project Duration
Stipulated Date of Commencement June 27 2008
Actual Date of Completion May 31 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,384,561.77
Awarded for ₹ 11,085,293.65
Final Cost of Project ₹ 8,211,565.00

Project highlights

Repairs works

 
Contractors
M/s. Chowgule Industries Limited
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 