Project Duration
Stipulated Date of Commencement February 23 2008
Stipulated Date of Completion /
Likely Date of Completion
May 07 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 28,927,260.38
Awarded for ₹ 27,788,946.00
 
Gallery Image
Contractors
M/s. Knchan Associates
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of Central Air Conditioning System for GMC Complex at Bambolim, Goa.

View Project
Similar Project

Supply, installation, testing and commisisoning of 125kva diesel generator set for primary health centre Pillem Dharbandora.

View Project
Similar Project

Steel Operation Theatre.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.