Project Duration
Stipulated Date of Commencement
February 23 2008
Stipulated Date of Completion /
Likely Date of Completion May 07 2008
Likely Date of Completion May 07 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,927,260.38
Awarded for
₹ 27,788,946.00
Contractors
M/s. Knchan Associates
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Medical Gas & Other Connected works for OTs.
View Project
Supply, Installation, Testing and Commissioning of negative pressure VRDL lab at Goa Medical College and Hospital, Bambolim.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa