Project Duration
Stipulated Date of Commencement June 15 2006
Stipulated Date of Completion /
Likely Date of Completion
January 14 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 49,834,633.00
Awarded for ₹ 42,696,401.00

Project highlights

Central air conditioning for Ward Block and other buildings at GMC, Bambolim.

 
Gallery Image
Contractors
M/s. Voltas Limited
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

SITC of medical gas supply system (MGSS)

View Project
Similar Project

Shadowless lights.

View Project
Similar Project

Supply Installation Testing & Commissioning of water Heater & Purifier

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.