Project Duration
Stipulated Date of Commencement
December 12 2011
Actual Date of Completion
May 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,528,636.00
Awarded for
₹ 5,976,204.30
Final Cost of Project
₹ 7,053,881.00
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
See Similar Projects
Medical gases & vacuum system works
View ProjectSteel Operation Theatre.
View ProjectElectrical work.
View Project