Project Duration
Stipulated Date of Commencement November 05 2014
Actual Date of Completion May 06 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 292,919,099.00
Awarded for ₹ 357,020,022.60
Final Cost of Project ₹ 416,060,328.31

Project highlights

New building for the CHC with 80 bed capacity

 
Contractors
M/s. MVR Infra Projects Pvt. Ltd
Consultants
M/s. Saolapurkar Associates
 