Project Duration
Stipulated Date of Commencement
February 15 2014
Stipulated Date of Completion /
Likely Date of Completion
Likely Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 35,090,528.00
Awarded for
₹ 33,945,797.37
Project highlights
Providing interior furniture, false ceiling, parttions and other furnishings
Contractors
M/s. T. S. Mistry,
Consultants
M/s KICONS