Project Duration
Stipulated Date of Commencement September 13 2018
Stipulated Date of Completion /
Likely Date of Completion
January 12 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,268,481.00
Awarded for ₹ 3,842,318.00

Project highlights

Upgradation work including tiling, roofing, painting etc for observatory