Project Duration
Stipulated Date of Commencement September 13 2018
Stipulated Date of Completion /
Likely Date of Completion
January 12 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,268,481.00
Awarded for ₹ 3,842,318.00

Project highlights

Upgradation work including tiling, roofing, painting etc for observatory

 
Gallery Image
Contractors
M/s.Atharva Infra Solutions
Gallery Image
Consultants
M/s.Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Office Building for Information Technology Department at Altinho, Panaji.

View Project
Similar Project

Construction of Building for Science Faculty at Goa University, Taleigao, Tiswadi Goa – Civil, electrification & land development work.

View Project
Similar Project

Painting and other ancillary works along major internal roads of Panaji city

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.